Contract Modifications: Upgrades, Renewals and Cancellations

Decide how an approved contract change affects the remaining revenue schedule, using three worked examples.

All articles

Choose the accounting treatment

Record the approval, effective date, changed promises and price. Approval may arise through enforceable written, oral or customary arrangements; a new invoice alone is not the assessment. An approved scope change with an unresolved price also needs an estimate and consideration of the variable-consideration constraint.

Three modification outcomes
Facts at the change dateTreatment
Added distinct goods or services, priced at their appropriate standalone selling pricesSeparate contract; retain the original accounting.
Not a separate contract; remaining goods or services are distinct from those already deliveredProspective accounting: combine unrecognised existing consideration with the modification consideration.
Remaining work is not distinct and belongs to a partially satisfied obligationUpdate the existing obligation and recognise a cumulative catch-up. Mixed arrangements may require both approaches.

IFRS 15, paragraphs 18–21 — Contract modifications. Related US GAAP references: ASC 606-10-25-10–13. The linked IFRS text is the 2021 issued edition.

Example 1: an additional workshop

A customer buys a January-to-December access service for €12,000. At 30 June, six equal monthly service periods have been delivered and €6,000 has been recognised. The customer then orders a distinct workshop for €2,000, its supported standalone selling price at that date.

Assume the workshop is separately beneficial and does not change or integrate with the access service. Account for the workshop separately. The original July-to-December schedule remains €1,000 per month. Recognise the €2,000 when the workshop obligation is satisfied, not when the additional order is signed.

Example 2: a discounted extension

Use the same original €12,000 access contract. At 30 June, the parties extend it for six additional months for €4,800. The original six remaining months and the extension provide the same service. Assume a supported standalone price of €1,000 per month, no customer-specific adjustment justifying the discount, and no other changes.

The additional price is not the appropriate standalone price, so the extension is not a separate contract for this example. Each remaining monthly service is distinct from services already delivered. Allocate the combined remaining amount evenly across the next twelve equal service periods.

Revised July-to-June schedule
CalculationAmount
Original consideration not yet recognised€6,000
Additional extension consideration€4,800
Total remaining consideration€10,800
€10,800 ÷ 12 remaining months€900 per month

Example 3: a catch-up that reduces revenue

An integrated construction obligation qualifies for recognition over time. Its original price is €1,000,000 and expected costs are €800,000. Eligible costs incurred are €400,000, giving 50% progress and €500,000 revenue recognised to date.

An approved change adds €200,000 to the price and €200,000 to expected costs. Assume the additional work is not distinct and cost-to-cost still faithfully measures progress. Costs incurred remain €400,000.

Cumulative catch-up calculation
CalculationResult
Revised total price€1,200,000
Revised expected costs€1,000,000
€400,000 ÷ €1,000,00040% complete
€1,200,000 × 40%€480,000 cumulative revenue
€480,000 − €500,000 already recognised−€20,000 adjustment

Handle renewals and cancellations on their facts

Assess whether a renewal exercises a material right already included in the original contract or represents a new purchase. For cancellation, inspect termination rights, penalties, refunds and remaining obligations before releasing any balance. A cancellation status in a system is not itself a revenue-recognition event.

  • Separate a change in enforceable scope from a revised estimate or an error correction.
  • Document the treatment of credits, outstanding receivables and any contract asset; do not automatically write off existing assets in a prospective modification.
  • Retain the original schedule, revised schedule, calculation, approval and effective date together. A reviewer should be able to explain every changed period.

FASB Revenue Recognition Implementation Q&As — Questions 7–8 address termination rights; 12–15 address material rights; 81 addresses existing contract assets on a prospective modification. Educational material; the Codification is authoritative US GAAP.